Sankar posted an Question
December 11, 2021 • 01:05 am 30 points
  • IIT JAM
  • Geology (GG)

44. for a dam site investigation, drilling was carried out up toa depth of 35m. the total length of recovered pieces (over 10cm) adds up to 21m. the rod of the

44. For a dam site investigation, drilling was carried out up toa depth of 35m. the total length of recovered pieces (over 10cm) adds up to 21m. The ROD of the foundation stone i 7o.

1 Answer(s) Answer Now
  • 0 Likes
  • 1 Comments
  • 0 Shares
  • comment-profile-img>
    Saurabh 1 best-answer

    Rock Quality Designation (RQD) can be given as = RQD(in percentage)= (Total length of recovered pieces/Drilling depth)×100 RQD= (21/35)×100= 0.6×100= 60% So RQD=60% is the answer ....

whatsapp-btn

Do You Want Better RANK in Your Exam?

Start Your Preparations with Eduncle’s FREE Study Material

  • Updated Syllabus, Paper Pattern & Full Exam Details
  • Sample Theory of Most Important Topic
  • Model Test Paper with Detailed Solutions
  • Last 5 Years Question Papers & Answers