44. For a dam site investigation, drilling was carried out up toa depth of 35m. the total length of recovered pieces (over 10cm) adds up to 21m. The ROD of the foundation stone i 7o.
  • 1 Answer(s)
  • 0 Likes
  • 1 Comments
  • Shares
  • Saurabh 1 thankyou
    Rock Quality Designation (RQD) can be given as = RQD(in percentage)= (Total length of recovered pieces/Drilling depth)×100 RQD= (21/35)×100= 0.6×100= 60% So RQD=60% is the answe...