ASSume the following regarding the development of a software system P: Estimated lines of code of P: 33, 480 LOC Average productivity for P 620 LOC per person-month Number of software developers :6 Average salary of a software developer: 50,000 per month If E, D and C are the estimated development effort (in person-months), estimated development time (in months), and estimated development cost (in Lac) respectively, then (E, D, C) (1) (54, 9, 27) (2)(48, 8, 24) (3)(60, 10, 30) (4) (42, 7, 21)
  • 1 Answer(s)
  • 1 Likes
  • 2 Comments
  • Shares
  • Sapna
    thank you
    Likes(0) Reply(0)
  • Komal bhati Best Answer
    detailed explanation.. see the image..
    • cropped5890958632031083007.jpg
    Likes(0) Reply(0)
Head Office :
MPA 44, 2nd floor, Rangbari Main Road,
Mahaveer Nagar II, Kota (Raj.) – 324005

Corporate Office:
212, F-1, 2nd Floor, Evershine Tower,
Amrapali Marg,
Vaishali Nagar, Jaipur (Raj.) – 302021

Mail: info@eduncle.com
All Rights Reserved © Eduncle.com