Assume the following regarding the development of a software system p: estimated lines of code of p: 33, 480 loc average productivity for p 620 loc per person-m

ASSume the following regarding the development of a software system P: Estimated lines of code of P: 33, 480 LOC Average productivity for P 620 LOC per person-month Number of software developers :6 Average salary of a software developer: 50,000 per month If E, D and C are the estimated development effort (in person-months), estimated development time (in months), and estimated development cost (in Lac) respectively, then (E, D, C) (1) (54, 9, 27) (2)(48, 8, 24) (3)(60, 10, 30) (4) (42, 7, 21)

1 Answer(s) Answer Now
  • 1 Likes
  • 2 Comments
  • 0 Shares
whatsapp-btn

Do You Want Better RANK in Your Exam?

Start Your Preparations with Eduncle’s FREE Study Material

  • Updated Syllabus, Paper Pattern & Full Exam Details
  • Sample Theory of Most Important Topic
  • Model Test Paper with Detailed Solutions
  • Last 5 Years Question Papers & Answers