The following information is given : Expected usage of 50,000 units in a period of 250 days Cost of processing an order ` 20 per order Carrying cost per unit ` 0.50 for the period lead time on an order : 5 days Company wants to keep a reserve supply of two day?s usage. How many units will be included in the reorder point ?
  • 1 Answer(s)
  • 0 Likes
  • 1 Comments
  • Shares
  • Dr. ashish kumar suri Best Answer
    please find the attach solution