When an activity is not connected to any of intermediate or end event and has no bearing on the project completion, is known as 

Choose Your Answer:
0 Attempts Submit Now
  • 1 Likes
  • 1 Comments
  • 0 Shares
  • comment-profile-img>
    Eduncle Best Answer

    Slack refers to the amount of time that an activity can be delayed from its earliest start time without delaying the project duration, if that activity and other activities take their estimated durations.