An __________ chart is a project schedule representation that presents project plan as a directed graph. The critical path is the __________ sequence of __________ tasks and it defines project __________.

Choose Your Answer:
0 Attempts Submit Now
  • 0 Likes
  • 1 Comments
  • 0 Shares
  • comment-profile-img>
    Eduncle Best Answer

    A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.