Q3. In a job shop operation, fivejobs may be performed on any of machines. The hours required for each job on each machine are sho below: machine Job 34 A13 14 16 10 B231512 Do161814 Eo12|13|12
  • 1 Answer(s)
  • 0 Likes
  • 1 Comments
  • Shares
  • Avijeet banerjee thankyou
    minimum cost is 45. explanation is given in the attachment.
    • cropped1871843242849223198.jpg
    • cropped4007491142125940475.jpg
    Likes(0) Reply(0)